GCN Home > October 25, 1999 issue
FEDERAL CONTRACT LAW
Contract categories don’t always tell the full
The tortuous history of an aborted contract for travel agent services offers useful lessons in federal contracts, including those for information technology.

A company called Travel Centre won a contract with the General Services Administration to be the preferred source for travel arrangements for federal workers in New England. Like commercial agents, the contractor would be compensated by commissions it earned for airline tickets and hotel reservations.

The solicitation had called for an indefinite-delivery, indefinite-quantity contract with a guaranteed minimum order of only $100. But the solicitation included a nonbinding estimate that, based on 1994 figures, the contractor would write 4,156 tickets and have sales of $1.8 million. Bidders were told to base their offers on this figure.

Business elsewhere

What GSA apparently knew, but didnt tell the bidders, was that the agencies that represented more than half the estimated business had already awarded separate travel agent contracts and would not use the GSA contract. Thus, the estimate was more than double what it should have been.

After Travel Centre had won the contract, its actual volume of sales fell far short of the estimates. Ultimately, it stopped performing, and GSA terminated the contract for default. Later, apparently realizing its fault in the matter, GSA converted the termination to one for the convenience of the government. This wasnt enough for Travel Centre, which filed a claim for damages. The contracting officer denied the claim, and the matter moved to the General Services Board of Contract Appeals.

In a 1997 ruling, the board held for Travel Centre in a split decision. In an opinion this year, also a split decision, the board awarded Travel Centre $42,546 in damages. Both times, the government asked the board to reconsider its ruling. Both times, the board declined to change the result, again over the objections of the dissenter.

Basically, the majority opinion held that the government had misrepresented the volume of business with faulty estimates and so had breached the contract. The dissenting opinions were by different judges but struck the same note.

The dissenters thought that the key to the case was in the type of contract awarded. They began and ended their analysis with the observation that the contracts were for an indefinite quantity, and were not requirements contracts. Because the government had ordered more than the $100 minimum quantity, its obligation to the contractor had been fulfilled, and the shortfall in business was of no consequence.
